Dysart Rd - APS Dry Utility

Project Name: Dysart Road APS Overhead to Underground Conversion

Construction Cost: $2,042,000.00

Description: This work consists of the installation of Arizona Public Service (APS), Century Link, Cox Communication and City ITS and Street Lighting conduit to prepare for an overhead to underground conversion along Dysart Road. Key Features of Work Included:

  • 1 mile of Duct Bank Work along Dysart Road

  • Extensive Utility Locating

  • 1 mile of Conduit Installation via Directional drill for Avondale Street Lighting

  • Asphalt Pavement Replacement (19mm Base Course HV) under 12.5mm ARAC

  • Installation of APS Manholes, Switch Cabinets, Capacitor Pads, and Transformer Pads

  • Installation of 5 Century Link Manholes

  • 60 Street Light Poles, Fixtures & Foundations

  • Minor Concrete Repairs allowing often times allowing for more informed driving decisions.