SR 202L South Mountain Freeway
Project Name: SR 202L South Mountain Freeway
Construction Cost: $31,013,849.77 (On-Going)
Owner: ADOT
Delivery Method: Public-Private-Partnership (P3)
Construction Dates: March 2017 - October 2020
Description: CSCI provided design collaboration on 22 miles of new freeway construction and four miles of freeway reconstruction. This included furnishing and installing two FMS node buildings / system, 32 ramp meter/detector stations, 15 Dynamic Message Signs, 58 CCTV cameras, two WIM systems, 634 loop detectors, 88 Gig-Ethernet switches, 650,000 feet of underground conduit, 370,000 feet of fiber optic cable, 125 fiber optic splice closures, 204 fiber termination panels and 1,300 LED light fixtures.